Click on the link below for information on the outbreak of Coronavirus Disease (COVID-19)

Alerts page detailed updates - Check back regularly for updated links & information

All Goshen municipal buildings closed to the public until further notice.

Broadband – Distribution Network Construction: April 12-April 16, 2021

Posted on April 12, 2021


weekly update


Weekly posts below indicate on which roads work is taking place.  Updates on this page are in reverse chronological order as information becomes available.  Note that all construction is weather dependent.

For a description of the work see “What is the Distribution Network?” below the weekly updates.


Week of April 12-April 16, 2021: 

  • Monday:  TriWire crews install MSTs on Fuller Road, Lilly Pond Lane and West Street.
  • Tuesday:  TriWire crews pull fiber on Ball Road and install MSTs on Sugar Maple Lane and West Street.
  • Wednesday:  TriWire crews lash fiber to the wire cable strand previously installed on Ball Road and install MSTs on West Street, East Street and Old Goshen Road.
  • Thursday: TriWire crews install MSTs on Ball Road and East Street

Week of April 5-April 9, 2021: 

  • Monday:  TriWire crews pull fiber and lash to the wire cable strand previously installed on East Street and Lilly Pond Lane.
  • Tuesday:  TriWire crews install MSTs on Fuller Road & Wing Hill Road. TriWire crews attach wire cable strand to utility company poles on Old Goshen Road.  TriWire crews pull fiber and lash to the wire cable strand previously installed on East Street.
  • Wednesday-Thursday:  TriWire crews pull fiber and lash to the wire cable strand previously installed on East Street and from the Hut east on Route 9.

Week of March 29-April 2, 2021:  Pull fiber and lash to wire cable strand previously installed, from Network Hut on Route 9 to West Street and up to Ball Road.  Also, pull fiber and lash to wire cable strand previously installed, from Network Hut on Route 9,  to South Main Street and continue on to East Street.

Week of March 22-26, 2021:

  • Monday: Wire cable strand attached to utility company poles on East Street, Sugar Maple Lane and Wing Hill Road.
  • Tuesday: Install grounding rods and do off road work on Berkshire Trail East and South Main Street.
  • Wednesday: Install grounding rods at various locations
  • Thursday:  Work on Lilly Pond Land cancelled and will be rescheduled due to road conditions on Ball Road.

Week of March 15-19, 2021:  TriWire crews attach wire cable strand to utility company poles on Route 9 and East Street.

Week of March 8-12, 2021:  TriWire crews attach wire cable strand to utility company poles on Ball Road, Lilly Pond Lane, South Main Street & the Main Street portion of Route 9 to West Street.

Week of March 1-5, 2021:  TriWire crews pull fiber and lash to the wire cable strand previously installed on West Street and Fuller Road.

Week of February 22-26, 2021:  TriWire crews attach wire cable strand to utility company poles on West Street and Fuller Road.


What is the Distribution Network?

The distribution network consists of all the existing utility poles that are on both public and private roads in Goshen.  The distribution network will connect back to the Network Hut and to the backbone, which is the main transmission line.  It does NOT include any of the service drops which will connect the distribution network to customer premises.  Service drops, or customer installations, are scheduled after sections of the distribution network are completed.

The distribution network is built out and completed in several phases:

  1.  Wire cable strand is strung and fastened from pole to pole.  Eight foot grounding rods are pounded into the ground and connected to the wire cable strand for proper electrical grounding at the appropriate locations.
  2.  Fiber optic cable is  lashed to the wire cable strand for support and resilience in the face of storms and windfall.
  3. Network extensions are installed at locations, off road, that do not meet the 170 foot minimum distance requirement between poles.
  4.  Splice cases are installed and splicing is done anywhere fiber needs to be joined together.
  5. Multi service terminals (MSTs) are installed, where needed, to allow multiple premises to be connected from one location.
  6. Testing and verification of fiber connections to the hut are done to be sure connections are working correctly.

Further updates to this post will  be made as new developments occur.

For a complete list of current (late 2020 & beyond) project updates click on Broadband postings in Town News & Announcements.

Additionally you can go to the Broadband High Speed Internet project page.


 

Close window