Goshen Sanitary Landfill Cap Repair

06/26/2018 - Received the following bid and construction schedule for the project:

07/03/18 - Receive Permit/Review comments from DEP

07/18/18 - Project listed in the Central register and local paper

07/25/18 - Pre-Bid site walk with contractors

08/15/18 - Bids Opened

08/27/18 - Notice to Proceed Issued by the Town

10/16/18 - Substantial Completion 

10/31/18 - Final Completion


6/23/2018 - By a vote of 52-10, voters have authorized the Town of Goshen to exempt the amounts required to pay for the repair of the landfill cap from Proposition 2 1/2.

6/18/2018 - The Clean Water Trust & MassDEP State Revolving Fund have approved Goshen's application for emergency funding for the remediation work to be done on the drainage over the landfill cap.  This will allow Goshen to have a low interest 2% loan for the amount borrowed for the project.  It will save the town approximately $63,000 dollars over the life of the loan.  There will also be an option to have a small amount of the loan principle repaid to the town.